|
Starlight Tower, Inc.
7000 Beach Plaza
St. Pete Beach, FL 33706
RESTORATION PROJECT: STATUS
REPORT (#2)
JULY, 2008
Our construction company (CPS) and our asbestos abatement
company (CTS), continue to have multiple teams moving through
the floors of our building accomplishing their different tasks.
We are still on schedule!
The leadership team continues to meet weekly with Vance (from
Resource), Bill Wales and Lynn Dopp so issues can be addressed
promptly. The Engineer (Santiago) attends the meetings every
other week, but is frequently on site inspecting the work.
As I reported before, the work is being done in multiple,
simultaneous phases. The current status of our beloved building
is as follows:
Walkway covering (river
rock) removal:
completed on all floors and stairwells.
Many areas of damage and cracks were found, including some areas
where the metal mesh (usually in the middle of the concrete
slab) was visible. A few areas of the 2” slab were so thin they
actually fell apart and required a plywood ‘patch’ to be placed
so we could walk on them.
North Side wall:
completely done, sealed and painted.
East Side:
-
Asbestos removed (abated) on floors 10 – 4. Team currently
working on the 3rd floor.
-
REPAIR PROCESS has now begun and is nearly complete on the
10th floor, will be moving to the 9th floor soon. Remember,
the repair process could not begin until the walkway
covering was removed and asbestos was abated, so that
‘soundings’ could be done to identify areas with damaged
rebar/metal. CPS anticipates bringing in additional workers
as the greater work of repairing (and possibly replacing)
joists begins on the 9th floor.
-
Cathodic protection system: continuity has been achieved on
floors 10 and 8 so far; 9th (and others) will follow the
repair process.
West (Gulf) Side:
-
As reported previously, the damage on this side of the
building continues to be greater than anticipated in some
areas and has required a few owners to be subject to the
cost of removal/replacement of shutters and/or windows. As
noted previously, if this is necessary the owner will be
notified. IF YOUR PHONE NUMBER OR CONTACT INFORMATION HAS
CHANGED, PLEASE BE SURE TO GIVE THE NEW INFORMATION TO
“RESOURCE PROPERTY MGMNT” SO YOU CAN BE CONTACTED PROMPTLY.
-
West side work is done by ‘stack’ (e.g. all the ’08 units)
since it requires a swing stage to be suspended from the
roof for each group. Progress to date: ‘08’ Stack: required
window removal from 2 units (one of which also required
shutter removal) to effect repairs to the building wall.
These and all other repairs to the ‘08’ stack have been
completed, all windows sealed and the first coats of paint
applied. Some damage to the kneewall of unit 108 was found
and will also be repaired.
-
‘07’ Stack: Only unit 107 required window & shutter removal,
again related to severe damage of the kneewall (as with 108,
probably related to previous 1st floor flooding). Repairs of
all identified damaged areas are currently underway on this
stack. Good news: Inspection of our first “open balcony”
(907) showed that both it and the unit below (807) were
structurally intact and did not require repair.
-
‘06’ Stack: swing stage will be moving here next week,
but
preliminary inspection seems to indicate most severe damage
is to 106 wall.
-
Again, if detailed inspection reveals a need to remove
windows and/or shutters, you will be notified. But remember,
we cannot tell in advance which units this will be – until
the swing stage moves to your ‘stack’ and the detailed, “up
close” inspections can be made.
Other Issues:
-
1. AC Grate coverings: The contractor has located a local
manufacturer who can make the new grate covers for us.
(Previous distributors were unable to produce covers in the
sizes needed). The manufacturer will produce a sample of
both the current grate pattern and a louvered one for us to
see.
-
2. Walkway drains: the original building plan called for the
walkways to drain water into the drainpipes that run down
the side of the building, with ‘overflow’ water going out
the ‘scuppers” (openings) in the walkway kneewalls. The
integrity of these drainpipes will be tested to ensure they
are patent and able to support this load of water before the
walkway sloping plan is designed. An alternate plan may be
to slope the walkway runoff through the scuppers if
necessary to avoid a potential ruptured drainage pipe. If
this is done, a ‘lip’ will be added to the edge of the
scupper to prevent the water from running down our freshly
painted walls.
In
short, although our building currently is looking a bit like a
patchwork quilt, it is heartening to know that these much needed
repairs are being done and her ‘facelift’ is underway!
~~ Lynn Dopp
|